10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.
These 10 free DRMP questions are organized by exam domain, so you can see how each part of the Decision & Risk Management Professional blueprint is tested. Reveal the answer and explanation under each question.
Domain 1: Basic Cost Engineering & Statistics and Economic Analysis
Question 1
An owner has spent $300,000 on a concept study that cannot be recovered. Proceeding now requires another $1,000,000 and would generate net receipts of $660,000 at the end of each of the next two years, relative to abandonment. Funding is available; there are no taxes, residual value, or other cash flows. At a 10% annual required return, which recommendation correctly applies incremental net present value?
Show answer & explanation
Correct answer: B - Proceed: excluding the sunk study cost gives an NPV of approximately +$145,000.
Question 2
A process-plant estimate uses detailed unit rates and is labeled Class 2 because most budgeted engineering hours have been spent. However, the equipment list, piping and instrumentation diagrams, and site layout remain substantially unresolved. Under AACE's process-industry classification approach, what evidence should control acceptance of the class label?
Show answer & explanation
Correct answer: D - The verified maturity and status of the scope-defining planning and design deliverables.
Question 3
A statistician reports a 95% confidence interval of $9.5-$10.5 million for the population mean cost of comparable installation jobs. The underlying jobs show substantial job-to-job variation. A director proposes $10.5 million as a P95 budget for the next job. Which correction addresses the director's error?
Show answer & explanation
Correct answer: C - Use the 95th percentile of a predictive cost distribution for an individual job.
Domain 2: Decision & Risk Practices
Question 4
A calibration review covers 100 completion forecasts for comparable projects. Each forecast gave a P10-P90 date range. Actual finishes were inside the ranges in 54 cases, earlier than P10 in 23, and later than P90 in 23. Project type and measurement basis had not materially changed. This pattern most strongly supports which diagnosis and response?
Show answer & explanation
Correct answer: D - Overconfidence: use the observed coverage to recalibrate the probabilities and reconsider range widths.
Question 5
A risk-neutral owner must choose a large or compact facility. High demand has probability 0.40 and low demand 0.60. The large facility's net present values are +$20 million and -$8 million in those states; the compact facility's are +$10 million and +$4 million. A demand study costs $4.6 million in present-value terms. It would arrive before selection but would only provide information, without changing the available facilities or their payoffs. Before investigating the study's accuracy, what can already be concluded?
Show answer & explanation
Correct answer: A - Reject the study: perfect information is worth $4.0 million at most.
Question 6
An owner can accept a guaranteed buyout or retain an asset with uncertain returns. After all costs and taxes, the two choices produce the same expected final wealth. The buyout produces a certain amount; retention produces genuinely variable wealth. The owner's utility of final wealth is increasing and strictly concave throughout the relevant range. Under that model, which preference is justified?
Show answer & explanation
Correct answer: D - Accept the buyout; it has greater expected utility.
Domain 3: Risk Management
Question 7
At a coastal terminal, the same port closure would delay two equipment deliveries due in the same shipping window. An analyst models independent closure events for the deliveries and adds a lump-sum site-overhead loss to each. The model also calculates site overhead from the simulated commissioning date. Which revision fixes both weaknesses?
Show answer & explanation
Correct answer: C - Sample one closure per trial, apply it to both deliveries, and calculate site overhead once from the resulting project duration.
Question 8
One hour before a commissioning pressure test, the independent shutdown trip fails its proof test. The approved test plan requires that trip to prevent a potentially fatal overpressure event. The sponsor offers to accept the risk because the initiating event is unlikely; no alternative protection has been assessed or authorized. What is the necessary immediate restriction?
Show answer & explanation
Correct answer: B - Hold the affected test until the trip is restored and verified.
Question 9
A funded supplier-response plan calls for a backup order if a factory inspection milestone is missed and delegates release authority to the procurement manager for premiums up to $250,000. The milestone has now been missed. The qualified backup supplier's premium is $180,000, and all specified release conditions are met. The original supplier still forecasts on-time delivery. What should the procurement manager do now?
Show answer & explanation
Correct answer: B - Release the authorized backup order now, documenting that the preapproved response trigger has been met.
Domain 4: Communication
Question 10
Finance and operations teams agree on the probability distributions for cost, completion, and throughput of two port-expansion schemes. They can reproduce each other's calculations, yet rank the schemes differently. Neither scheme violates a mandatory requirement. The facilitator's next useful task is to:
Show answer & explanation
Correct answer: A - Clarify the value trade-offs and risk preferences the authorized decision-maker wants applied.
That's 10 of 1,030
The full bank has 1,020 more DRMP questions with explanations.